Gateway Improvements

Visually appealing gateways with welcome signs and landscaping create a positive first impression and set the tone for what's to come. They make people feel welcome and excited about exploring the city. In Pelham, we consider our gateways the introduction to our brand story, and significant improvements are planned to reflect the true essence of the city.  It's a way of saying, "This is who we are, and we want you to experience it."

Project at a Glance

Plans call for updates at all of the city's major entry points. The first two, which were included in the FY 2024 budget are on US-31 at the northern and southern borders. The gateways will include signage with a mix of natural and modern elements, landscaping, and lighting. Part of the landscaping will include wildflower meadows with flora species native to Alabama.

Project Cost

  • $639,500

*This is a multi-year initiative, and the cost indicates the project listed.

Project Timeline

US-31 Northern Gateway

  • Right-of-Way permitting - Complete
  • Construction - Complete
  • Landscaping - Estimated completion: December 2025

CR-11 Gateway

  • Right-of-Way permitting - Complete
  • Construction - Complete
  • Landscaping - Estimated completion: December 2025

*A more detailed construction schedule will be available as the project timeline advances

  1. #ExplorePELHAMAL

  1. Pelham Alabama Homepage

Contact Us

  1. City of Pelham
    3162 Pelham Pkwy
    Pelham, AL 35124
    Phone: 205.620.6400
    Fax: 205.620.6548

Government Websites by CivicPlus®
Arrow Left Arrow Right
Slideshow Left Arrow Slideshow Right Arrow